On the map
State significant development

Penrith HV Battery Energy Storage System

A 100 MW battery at Castlereagh Road, Penrith

Under way: at response to submissionsEnergy: batteriesDistrict scale

Where it is in the process

At response to submissions

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (current stage)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Penrith HV BESS EIS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100 MW battery at Castlereagh Road, Penrith

The proponent proposes a battery energy storage system with a capacity of up to 100 MW and 200 MWh at 2235-2249 Castlereagh Road, Penrith, in the Penrith City Council area. It would use 48 lithium-ion battery containers on about 1 ha beside the existing Penrith Transmission Substation, with 7 m high noise walls. The environmental impact statement (EIS) gives an estimated development cost of about $85 million. Construction would take about 15 months, with a peak workforce of 35 to 40 people.

The EIS is dated 20 Oct 2025 and was exhibited. It drew 63 submissions: 60 objecting and 3 commenting. The proponent is now responding to the submissions and preparing an amendment report. Next, the department assesses the project with advice from other agencies, then it is decided. No decision date is given.

Estimated development cost
$85MPenrith HV BESS EIS
Battery power capacity
100 MWPenrith HV BESS EIS
Battery storage capacity
200 MWhPenrith HV BESS EIS
Battery containers
48 containersPenrith HV BESS EIS
Development footprint
1 haPenrith HV BESS EIS
Noise wall height
7 mPenrith HV BESS EIS
Peak construction workforce
40 full-time equivalent workersPenrith HV BESS EIS
Submissions objecting
60 submissionsPortal page

The department's description

Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 100MW/200MWh and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

63 submissions: 50 from the public, 12 from organisations and 1 from public authorities

Object60
Support0
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

50 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs4
EIS24
Response to Submissions1
Agency Advice19

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.