On the map
State significant infrastructure

Muswellbrook Pumped Hydro Energy Storage

A 500 MW pumped hydro power station near Muswellbrook

Under way: at prepare eisEnergy: batteriesDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Issued SEARs on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 500 MW pumped hydro power station near Muswellbrook

The proponent proposes a pumped hydro power station with a capacity of 500 MW, with upper and lower reservoirs, a grid connection and other supporting infrastructure. The site is at 250 Dolahentys Road, McCullys Gap, about 4 km north-east of Muswellbrook, in the Muswellbrook Shire. The project has been declared critical State significant infrastructure. No capital investment, job numbers or reservoir sizes are stated.

The Secretary's environmental assessment requirements (SEARs) were issued on 17 Nov 2025. They tell the proponent what its environmental impact statement (EIS) must cover, including biodiversity, water, heritage, traffic, noise and visual impacts, bushfire and flooding. The proponent is now preparing the EIS. Next, the EIS is lodged and exhibited, and the public can make submissions. There are no submissions yet. The department then assesses the project.

Power station capacity
500 MWPortal page

The department's description

Muswellbrook Pumped Hydro Energy Storage Project, which includes the development of a 500 megawatt pumped hydro power station, upper and lower reservoirs, grid connection and ancillary infrastructure. This project has been declared CSSI.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.