On the map
State significant development

Murrumburrah Battery Energy Storage System

A 100 MW battery at Substation Road, Murrumburrah

Under way: at prepare eisEnergy: batteriesDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100 MW battery at Substation Road, Murrumburrah

The proponent proposes a battery energy storage system of about 100 MW and 400 MWh on Lot 715 DP 753624, Substation Road, Murrumburrah, in the Hilltops Council area. The development site is about 4.5 ha within a 21 ha lot now used for farming. It would have containerised batteries, a control building, a cable connection to the Murrumburrah substation and a new access from Substation Road. The scoping report expects up to 75 construction jobs and 2 to 3 operational jobs, and a project life of about 20 years. No capital investment is stated.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). A scoping report was lodged and the Secretary's environmental assessment requirements (SEARs) were issued and later updated. Agencies have given advice. No submissions have been made. Next, the EIS is to be exhibited for public submissions, then the proponent responds and the department assesses it.

Battery power capacity
100 MWScoping Report
Battery storage capacity
400 MWhScoping Report
Development site area
4.5 haScoping Report
Host lot area
21 haScoping Report
Construction jobs
75 jobsScoping Report
Project life
20 yearsScoping Report

The department's description

Development of a 100 MW / 400 MWh battery storage system and associated infrastructure including grid connection.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Where it is

Suburb
Murrumburrah
Council area
Hilltops

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.