Mount Piper Power Station - Ash Placement

Decided: approved on 16 Feb 2012Other

Where it is in the process

Approved on 16 Feb 2012

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination16 Feb 2012 (done)
  8. Approved16 Feb 2012

What it proposes

The department's description

Construction and operation of the Lamberts North Ash Repository (LNAR) and Lamberts South Ash Repository (LSAR) at the Mt Piper Power Station.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 2 - Extended Operational HoursMP09_0186-Mod-2

Decided: approved on 5 Nov 2024 by the department (director) · 1 submission

Extend the operational hours to 24 hours a day, 7 days a week.

Its 21 documents

Its page on the Planning Portal

MOD 1 - Lamberts North Ash Repository UpgradesMP09_0186-Mod-1

Decided: approved on 21 Sep 2021 by the department (director) · 12 submissions

Staged upgrades to the approved Lamberts North Ash Repository (LNAR), construction of multipurpose storage ponds to manage any likely leachate from the LNAR, and minor amendments to the approved LNAR boundary and reducing its footprint by 5 ha.

Its 18 documents

18 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Recommendation4

See the 4 documents on the Planning Portal

Determination6

See the 6 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.