Mount Piper Power Station - Ash Placement
Where it is in the process
Approved on 16 Feb 2012
What it proposes
The department's description
Construction and operation of the Lamberts North Ash Repository (LNAR) and Lamberts South Ash Repository (LSAR) at the Mt Piper Power Station.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Modifications
2 changes to the project after its decision, each assessed as a case of its own, newest first.
MOD 2 - Extended Operational HoursMP09_0186-Mod-2
Extend the operational hours to 24 hours a day, 7 days a week.
Its 21 documents
21 documents in 8 folders, each on the NSW Planning Portal
Early Consultation1
Notice of Exhibition2
Modification Application4
Response to Submissions2
Agency Advice6
Additional Information2
Determination3
Consolidated Consent1
MOD 1 - Lamberts North Ash Repository UpgradesMP09_0186-Mod-1
Staged upgrades to the approved Lamberts North Ash Repository (LNAR), construction of multipurpose storage ponds to manage any likely leachate from the LNAR, and minor amendments to the approved LNAR boundary and reducing its footprint by 5 ha.
Its 18 documents
18 documents in 6 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application4
Response to Submissions2
Recommendation4
Determination6
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
64 documents in 10 folders, each on the NSW Planning Portal
Application2
Submissions13
Response to Submissions1
Determination2
Management Plans and Strategies9
Notifications2
Other Documents3
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.