Ivanhoe Battery Energy Storage System
A 700 MW battery at Boulder Road, Portland
Where it is in the process
At prepare eis
What it proposes
AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 700 MW battery at Boulder Road, Portland
The proponent proposes a grid-scale battery energy storage system on part of the former Ivanhoe Colliery, about 22 kilometres north-west of Lithgow in the Lithgow City Council area. It would have a discharge capacity of up to 700 MW and up to 2.8 GWh of storage. It would include lithium-ion battery modules, inverters, a connection to the nearby Mt Piper Substation, fire detection and suppression equipment and access roads. The project area is about 51 ha. Construction would take about 20 months, and the operating life would be 25 years. No capital investment or job numbers are stated.
The proponent lodged a scoping report in May 2026, and the Secretary's environmental assessment requirements (SEARs) were issued, with agency advice on them. The proponent is now preparing an environmental impact statement (EIS). Next, the EIS is exhibited and the public can make submissions. No submissions have been made yet. The Minister or the Independent Planning Commission would decide.
- Discharge capacity
- 700 MWScoping Report
- Storage capacity
- 2.8 GWhScoping Report
- Project area
- 51 haScoping Report
- Indicative battery footprint
- 21 haScoping Report
- Construction period
- 20 monthsScoping Report
- Operational life
- 25 yearsScoping Report
The department's description
Construction and operation of a grid-scale BESS including battery modules, inverters and associated infrastructure with a discharge capacity of up to 700 megawatts (MW) up to 2.8 gigawatt hours (GWh).
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
15 documents in 3 folders, each on the NSW Planning Portal
Request for SEARs1
Agency Advice13
- CASA advice on SEARs
- DCCEEW CPHR advice on SEARs
- DCCEEW MCEF advice on SEARs
- DCCEEW Water advice on SEARs
- DPIRD advice on SEARs
- FRNSW advice on SEARs
- HNSW ACH advice on SEARs
- HNSW EH advice on SEARs
- Lithgow Council advice on SEARs
- NSW Resources advice on SEARs
- NSW SES advice on SEARs
- TfNSW advice on SEARs
- WaterNSW advice on SEARs
What's near it
Its point is approximate (the register's own, to about a kilometre), and so are these.
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.