Ivanhoe Battery Energy Storage System

A 700 MW battery at Boulder Road, Portland

Under way: at prepare eisEnergy: batteriesRegional scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 700 MW battery at Boulder Road, Portland

The proponent proposes a grid-scale battery energy storage system on part of the former Ivanhoe Colliery, about 22 kilometres north-west of Lithgow in the Lithgow City Council area. It would have a discharge capacity of up to 700 MW and up to 2.8 GWh of storage. It would include lithium-ion battery modules, inverters, a connection to the nearby Mt Piper Substation, fire detection and suppression equipment and access roads. The project area is about 51 ha. Construction would take about 20 months, and the operating life would be 25 years. No capital investment or job numbers are stated.

The proponent lodged a scoping report in May 2026, and the Secretary's environmental assessment requirements (SEARs) were issued, with agency advice on them. The proponent is now preparing an environmental impact statement (EIS). Next, the EIS is exhibited and the public can make submissions. No submissions have been made yet. The Minister or the Independent Planning Commission would decide.

Discharge capacity
700 MWScoping Report
Storage capacity
2.8 GWhScoping Report
Project area
51 haScoping Report
Indicative battery footprint
21 haScoping Report
Construction period
20 monthsScoping Report
Operational life
25 yearsScoping Report

The department's description

Construction and operation of a grid-scale BESS including battery modules, inverters and associated infrastructure with a discharge capacity of up to 700 megawatts (MW) up to 2.8 gigawatt hours (GWh).

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.