On the map
State significant development

Mount Lambie Wind Farm

A 20-turbine wind farm and battery on Curly Dick Road

Under way: at prepare eisEnergy: windDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 20-turbine wind farm and battery on Curly Dick Road

The proponent proposes a wind farm of up to 20 turbines, with blade tips 250 to 285 m above ground, spread over about 2,540 ha, about 12 km south-west of Wallerawang in the Lithgow City Council area. It would have a capacity of up to 200 MW and include a 100 MW battery that can run for up to six hours. Peak construction would employ around 150 people and 6 to 8 workers would run it. No capital investment is stated.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). The proponent's scoping report is dated 10 Jun 2025, and the Secretary's environmental assessment requirements (SEARs) have been issued. The EIS has not yet been exhibited, so there are no submissions. Next, the EIS is exhibited for public submissions, then the proponent responds and the department assesses the project.

Wind turbines
20 turbinesScoping Report
Generation capacity
200 MWScoping Report
Battery power capacity
100 MWScoping Report
Project area
2,540 haScoping Report
Peak construction workforce
150 jobsScoping Report
Maximum turbine blade-tip height
285 mScoping Report

The department's description

Development of a wind energy generation project with up to 20 wind turbines, with energy storage and associated infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.