On the map
State significant development

Mixed use commercial and residential development, 24 Parkes St, Harris Park

A 271-home tower at 24 Parkes Street, Harris Park

Under way: at prepare eisHomesNeighbourhood scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its SSD-82652460 - Industry Specific SEARs - Housing on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 271-home tower at 24 Parkes Street, Harris Park

The proponent proposes to demolish the existing structure at 24 Parkes Street, Harris Park, in the City of Parramatta, and build a mixed use commercial and residential tower. It would have 271 dwellings, including 41 affordable dwellings, along with commercial floor space and basement parking. No capital investment, building height or floor area is stated.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) were issued on 22 Apr 2025, and a later extension letter is listed. The requirements ask the EIS to cover issues including built form, overshadowing, visual impact, transport, noise, flooding and Aboriginal cultural heritage. Next, the proponent lodges the EIS, which is exhibited for public submissions. No submissions have been made yet. The department then assesses the project.

Dwellings
271 dwellingsPortal page
Affordable dwellings
41 dwellingsPortal page

The department's description

Demolition of existing structure and construction of a mixed use commercial and residential tower comprising 271 dwellings, including 41 affordable, commercial floor space and basement parking.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.