State significant development

Western Sydney University - Innovation Hub

Decided: approved on 21 Nov 2019Education

Where it is in the process

Approved on 21 Nov 2019

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination21 Nov 2019 (done)
  9. Approved21 Nov 2019

What it proposes

The department's description

Construction of a 19-storey mixed-use development incorporating education uses for Western Sydney University, commercial and retail uses. The proposal also includes landscaping, public domain, services augmentation and infrastructure works.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

8 submissions: 8 from public authorities

Object0
Support0
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

5 changes to the project after its decision, each assessed as a case of its own, newest first.

WSU Innovation Hub MOD 5 - Signage zonesSSD-9670-Mod-5

Decided: approved on 5 Mar 2021 by the department (director)

Amendment to approved signage zones.

Its 10 documents

10 documents in 4 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

WSU Innovation Hub MOD 4 - Design refinementsSSD-9670-Mod-4

Decided: approved on 23 Dec 2020 by the department (director)

Design amendments to ground floor retail component, building entry portals and basement parking.

Its 13 documents

13 documents in 3 folders, each on the NSW Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

WSU Innovation Hub MOD 3 - Signage and stormwaterSSD-9670-Mod-3

Decided: approved on 28 Aug 2020 by the department (director)

Amend conditions relating to signage and stormwater infrastructure.

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

WSU Innovation Hub MOD 2 - Design refinementsSSD-9670-Mod-2

Decided: approved on 6 May 2020 by the department (director)

Amendment to the facade of the building and other minor design modifications as a result of the detailed design process.

Its 6 documents

6 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

WSU Innovation Hub MOD 1 - Construction hoursSSD-9670-Mod-1

Decided: approved on 4 Mar 2020 by the department (director)

Amendment to conditions regarding bicycle parking (conditions A2 and B30), wind tunnel testing (condition B12) and construction hours (condition C4).

Its 13 documents

13 documents in 4 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.