On the map
State significant infrastructure

McPhillamys Water Supply Pipeline

A water supply pipeline near Blayney for the McPhillamys mine

Under way: at prepare eisMiningNeighbourhood scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its 2025-12-15 SSI Issued SEARs on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A water supply pipeline near Blayney for the McPhillamys mine

The proponent, LFB Resources NL, proposes a water supply pipeline between the Angus Place Colliery and the McPhillamys mine site, about 8 km north-east of Blayney. The route runs through the Blayney Shire, Lithgow City and Bathurst Regional council areas. It is one of three enabling projects for the McPhillamys Gold Project, with an electricity transmission line and a waste landform. No length, capacity or capital investment is stated.

The department issued the Secretary's environmental assessment requirements (SEARs) on 15 Dec 2025. The proponent is now preparing an environmental impact statement (EIS), which must cover land and soil, water, biodiversity, heritage, traffic and bushfire. The EIS must also include a cost estimate and job numbers. Next, the EIS is to be exhibited and the public can make submissions. There are no submissions yet. The SEARs expire if no EIS is lodged within two years of issue.

The department's description

Development of a water supply pipeline between the Angus Place Colliery and the McPhillamys mine site.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.