Brewongle Solar Farm

A 90 MW solar farm and battery at 315 Tarana Road, Brewongle

Decided: approved on 25 Sep 2026Energy: solarNeighbourhood scale

Where it is in the process

Approved on 25 Sep 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination25 Sep 2026 (done)
  9. Approved25 Sep 2026

What it proposes

AI summary. Written from this project's page and its Assessment Report and Conditions of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 90 MW solar farm and battery at 315 Tarana Road, Brewongle

The project is a solar farm with a generating capacity of 90 MW and a battery energy storage system, at 315 Tarana Road, Brewongle, south-east of Bathurst in the Bathurst Regional Council area. It has about 180,000 solar panels, an on-site substation and a connection to an existing 132 kV transmission line. The consent limits the battery to 90 MW and 180 MWh. The department's report gives up to 5 operational jobs. No capital investment figure is legible.

The environmental impact statement (EIS) was exhibited from 23 May 2025 to 20 Jun 2025. The portal records 59 submissions: 56 objecting, 1 supporting and 2 commenting. The council did not object. The department found the project approvable, and its Acting Executive Director approved it on 25 Sep 2026 as the Minister's delegate. Next, the proponent must meet the consent's conditions, including road upgrades before construction.

Solar farm capacity
90 MWPortal page
Solar panels
180,000 panelsAssessment Report
Battery maximum discharge capacity
90 MWConditions of Consent
Battery maximum storage capacity
180 MWhConditions of Consent
Maximum heavy vehicle movements a day in construction
80 movementsConditions of Consent
Submissions
59 submissionsPortal page

The department's description

Development of a 90 MW solar farm with energy storage and associated infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

59 submissions: 50 from the public, 8 from organisations and 1 from public authorities

Object56
Support1
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

87 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs1
EIS17
Response to Submissions12
Agency Advice44
Additional Information8
Determination3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.