On the map
State significant development

Mayfair Solar Farm

A 60 MW solar farm and battery at Jacksons Lane, Stubbo

Under way: at assessmentEnergy: solarNeighbourhood scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its EIS - Final - Redacted on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 60 MW solar farm and battery at Jacksons Lane, Stubbo

The proponent proposes to build, operate and decommission a 60 MW solar farm with associated infrastructure and a battery at 204 Jacksons Lane, Stubbo, in the Mid-Western Regional Council area. The environmental impact statement (EIS) of November 2024 lists a substation, a connection to the network, an upgrade of Jacksons Lane and temporary workforce accommodation. No capital investment, site area or job numbers are stated.

The EIS was exhibited, with the exhibition period extended, and drew 87 submissions: 86 objecting and 1 commenting. The proponent has responded to submissions and to requests for more information. The case is now at the stage of more information being required, and no date is given. Next, the department assesses the project with advice from other agencies, and then the department or the Independent Planning Commission decides it.

Solar farm capacity
60 MWPortal page
Public submissions
87 submissionsPortal page
Submissions objecting
86 submissionsPortal page

The department's description

The construction, operation and decommissioning of a 60MW solar farm including associated infrastructure and battery

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

87 submissions: 73 from the public, 13 from organisations and 1 from public authorities

Object86
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

85 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition2
Request for SEARs1
SEARs1
EIS25
Response to Submissions10
Agency Advice38
Additional Information8

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.