On the map
State significant development

Mallee Wind Farm

A 76-turbine wind farm and battery at Mallee, near Buronga

Under way: at assessmentEnergy: windDistrict scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 76-turbine wind farm and battery at Mallee, near Buronga

The proponent proposes a wind farm with up to 76 wind turbines, each up to 280 m tall to the blade tip, and a single 100 MW / 200 MWh battery. The project would have an installed generation capacity of up to 402 MW. It is on Arumpo Road, Mallee, about 16 km north-east of Buronga in the Wentworth Shire. It also includes substations, access tracks, power lines, a temporary workers' accommodation facility and road upgrades. No capital investment or job numbers are stated.

The environmental impact statement (EIS) is dated November 2024. The project drew 123 submissions: 116 objecting, 4 supporting and 3 commenting. The proponent has since amended the project, with a second amendment report in October 2026, and given further information. The department is assessing it. Next come the department's assessment report and a decision.

Wind turbines
76 turbinesEnvironmental Impact Statement
Installed generation capacity
402 MWEnvironmental Impact Statement
Maximum blade-tip height
280 mEnvironmental Impact Statement
Battery power capacity
100 MWEnvironmental Impact Statement
Submissions objecting
116 submissionsPortal page

The department's description

Construction and operation of a wind farm with up to 76 wind turbines, battery storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

123 submissions: 100 from the public, 22 from organisations and 1 from public authorities

Object116
Support4
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

92 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs2
SEARs17
EIS21
Response to Submissions13
Agency Advice17
Amendments8
Additional Information13

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.