Gol Gol Battery Energy Storage System

A 1,500 MW battery on Arumpo Road, near Gol Gol

Under way: at sears expiredEnergy: batteriesRegional scale

Where it is in the process

  1. Prepare Scoping Report (to come)
  2. SEARs (to come)
  3. Prepare EIS (to come)
  4. Exhibition (to come)
  5. Collate Submissions (to come)
  6. Response to Submissions (to come)
  7. Assessment (to come)
  8. Recommendation (to come)
  9. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Gol Gol BESS Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 1,500 MW battery on Arumpo Road, near Gol Gol

The proponent proposes a battery energy storage system of up to 1,500 MW / 12 GWh at 664 Arumpo Road, Wentworth Shire, about 10 km north-east of Mildura. It would sit next to the Buronga substation, with new substations and a new connection to the existing 220 kV transmission line. The project investigation area is about 1,500 ha, and the proposed development corridor is about 780 ha. No capital investment, job numbers or final layout are stated.

The proponent lodged a scoping report in May 2024 to request the Secretary's environmental assessment requirements (SEARs). The SEARs were issued but have since expired. No environmental impact statement (EIS) is listed, so the project has not been exhibited and has received no submissions. If the proponent wants to proceed, it would need new requirements and then an EIS. The scoping report says the EIS would assess biodiversity, Aboriginal heritage, visual impact, social impact and traffic in detail.

Battery power capacity
1,500 MWGol Gol BESS Scoping Report
Battery storage capacity
12 GWhGol Gol BESS Scoping Report
Project investigation area
1,500 haGol Gol BESS Scoping Report
Proposed development corridor
780 haGol Gol BESS Scoping Report

The department's description

Development of a 1500 MW / 12 GWh battery storage system and associated infrastructure including grid connection.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.