A 450 MW solar farm and battery near Tarago

Under way: at prepare eisEnergy: solarDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its AA_Scoping Summary Table on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 450 MW solar farm and battery near Tarago

The proponent proposes to build, run and later decommission a solar farm with a capacity of up to 450 MW, together with a battery energy storage system of up to 450 MW / 3600 MWh and ancillary infrastructure. The site is about six kilometres south-west of Tarago and 17 kilometres north-east of Bungendore, in the Goulburn Mulwaree and Queanbeyan-Palerang Regional council areas. No capital investment, site area or job numbers are stated.

The project is at the stage where the proponent prepares its environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) have been issued, with supplementary requirements and advice from agencies and both councils. Next, the proponent lodges the EIS, which is exhibited for public submissions. None have been made yet. The department then assesses the project.

Solar farm capacity
450 MWPortal page
Battery power capacity
450 MWPortal page
Battery storage capacity
3,600 MWhPortal page

The department's description

Construction, operation, and decommissioning of a Solar Farm with a capacity of up to 450 MW, a battery energy storage system (BESS) with a capacity of up to 450 MW / 3600 MWh, and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.