On the map
State significant development

Lake Munmorah Battery Energy Storage System

A 100 MW battery at 395 Pacific Highway, Lake Munmorah

Under way: at prepare eisEnergy: batteriesDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100 MW battery at 395 Pacific Highway, Lake Munmorah

The proponent, Ausgrid, proposes a battery energy storage system with a capacity of up to 100 MW and 400 MWh at its existing Lake Munmorah zone substation at 395 Pacific Highway, Lake Munmorah, in the Central Coast Council area. The battery area is about 1.1 ha on a lot of about 1.26 ha. It would connect to the substation by a 33 kV underground cable. No capital investment or job numbers are stated.

The proponent's scoping report is dated 6 Aug 2026, and the Secretary's environmental assessment requirements (SEARs) have been issued. Agencies have given advice on them. The proponent is now preparing an environmental impact statement (EIS). Next, the EIS is to be exhibited for public submissions, and the department then assesses the project. No submissions have been made yet.

Battery power capacity
100 MWScoping Report
Battery storage capacity
400 MWhScoping Report
Lot size
1.26 haScoping Report
Battery development area
1.1 haScoping Report

The department's description

Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 100 MW / 400 MWh and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.