Chain Valley Extension Project- SSD-5465

Decided: decidedMining

Where it is in the process

At determination

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination (current stage)

What it proposes

The department's description

Extension to approved extraction area of CVC Colliery, increased rate of production and extension of approved mining period by 14 years.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

15 submissions: 15 from the public

Object0
Support15
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Chain Valley Colliery MOD 4 - Boundary ExtensionSSD-5465-Mod-4

Decided: approved on 5 Aug 2021 by the department (director) · 14 submissions

Extend the consent boundary to incorporate the Northern Mining Area (NMA). Transfer coal extracted from the NMA to the CVC pit top.

Its 17 documents

17 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Chain Valley MOD 3 - Increased ProductionSSD-5465-Mod-3

Decided: approved on 26 Jun 2020 by the Independent Planning Commission · 23 submissions

To increase the transport of product coal from Chain Valley Colliery to Mannering Colliery from 1.3 to 2.1 million tonnes per annum.

Its 22 documents

22 documents in 6 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice12

See the 12 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Recommendation2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Chain Valley Extension Project MOD 2 - Chain Valley CollierySSD-5465-MOD-2

Decided: approved on 16 Dec 2015 by the department (executive director) · 11 submissions

Increase rate of coal extraction from 1.5 Mtpa with additional coal to be transported via Mannering Colliery to Vales Point Power Station. Mine design changes.

Its 17 documents

Its page on the Planning Portal

Chain Valley Extension Project MOD 1 - Mod 1SSD-5465-MOD-1

Decided: approved on 27 Nov 2014 by the department (executive director) · 14 submissions

Construction of an underground linkage between Chain Valley and Mannering Collieries for coal transportation.

Its 7 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.