On the map
State significant development

Chain Valley Colliery Consolidation Project

Consolidating Chain Valley and Mannering collieries, Lake Macquarie

Decided: approved on 9 Apr 2026MiningDistrict scale

Where it is in the process

Approved on 9 Apr 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination9 Apr 2026 (done)
  9. Approved9 Apr 2026

What it proposes

AI summary. Written from this project's page and its Development consent - SSD-17017460 and Chain Valley Consolidation Project Assessment Report-Final on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Consolidating Chain Valley and Mannering collieries, Lake Macquarie

The project merges the consents for Chain Valley Colliery and Mannering Colliery, underground coal mines on the southern shore of Lake Macquarie, in the Central Coast and Lake Macquarie City council areas. It would extend mine life by two years to 31 December 2029 and raise throughput at the Mannering pit top from 2.1 to 2.8 million tonnes a year. It would also allow more secondary coal extraction under the lake, within approved mining areas. The department says it would retain about 390 direct jobs. No capital investment is stated.

The environmental impact statement (EIS) was exhibited from 18 Nov 2022 and drew 182 submissions: 134 objecting, 46 supporting and 2 commenting. The department's assessment report of December 2025 gave no recommendation and set out draft conditions. The Independent Planning Commission approved the project on 9 Apr 2026, with conditions. Next, the proponent must meet those conditions, including limits on subsidence, noise and air quality.

Mine life extension
2 yearsChain Valley Consolidation Project Assessment Report-Final
Mannering pit top throughput (proposed)
2.8 million tonnes a yearChain Valley Consolidation Project Assessment Report-Final
Direct jobs retained
390 jobsChain Valley Consolidation Project Assessment Report-Final
Indirect jobs
1,000 jobsChain Valley Consolidation Project Assessment Report-Final
Site area
3,030 haChain Valley Consolidation Project Assessment Report-Final
Public submissions
182 submissionsPortal page

The department's description

Consolidate Chain Valley Colliery and Mannering Colliery consents. Align approved extraction and production rates at both collieries.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

182 submissions: 174 from the public, 7 from organisations and 1 from public authorities

Object134
Support46
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

98 documents in 12 folders, each on the NSW Planning Portal

Notice of Exhibition1
Early Consultation1
Request for SEARs5
SEARs5
EIS21
Response to Submissions2
Agency Advice24
Amendments1
Additional Information24
Recommendation4
Determination2
Management Plans and Strategies8

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.