On the map
Part 4 development

HVO North - West Pit Consent 2003

Decided: decidedMining

Where it is in the process

At determination

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (current stage)

What it proposes

The portal gives no description.

Modifications

8 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 4 - Fine Reject EmplacementDA450-10-2003-Mod-4

Decided: approved by the Minister

Its 16 documents

Its page on the Planning Portal

Mod 3 - Extension of Carrington PitDA450-10-2003-Mod-3

Decided: approved by the Minister

Its 21 documents

Its page on the Planning Portal

Mod 8 - Extension of timeDA450-10-2003-Mod-8

Decided: approved on 24 Apr 2025 by the department (executive director) · 101 submissions

Modification for an extension of time for mining operations for an additional 18 months through to 31 December 2026.

Its 28 documents

28 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application12

See the 12 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice8

See the 8 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

HVO North MOD7 - Administration modificationDA450-10-2003-Mod-7

Decided: approved on 28 Jul 2017 by the department (director)

/

Its 7 documents

Its page on the Planning Portal

HVO North MOD6 - Backfill Pit Material ChangeDA450-10-2003-Mod-6

Decided: approved on 25 Jan 2017 by the department (director)

/

Its 14 documents

Its page on the Planning Portal

HVO North MOD5 - Communications and Baisin ApprovalDA450-10-2003-Mod-5

Decided: approved on 9 Dec 2016 by the department (director)

/

Its 11 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

46 documents in 6 folders, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

Management Plans and Strategies26

See the 26 documents on the Planning Portal

Reports6

See the 6 documents on the Planning Portal

Independent Reviews and Audits5

See the 5 documents on the Planning Portal

Notifications1

See the document on the Planning Portal

Other Documents6

See the 6 documents on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.