On the map
State significant development

Ravensworth Coal Operations

Decided: approved on 11 Feb 2011Mining

Where it is in the process

Approved on 11 Feb 2011

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination11 Feb 2011 (done)
  8. Approved11 Feb 2011

What it proposes

The portal gives no description.

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Ravensworth Coal (Mod 4) - GRAWTS Stage 2MP09_0176-Mod-4

Decided: approved on 15 May 2023 by the department (director) · 3 submissions

Transfer of tailings to Liddell Mine

Its 16 documents

16 documents in 5 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice9

See the 9 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Ravensworth Coal MOD3 - Tailings PipelineMP09_0176-Mod-3

Decided: approved on 16 Feb 2016 by the department (director)

/

Its 11 documents

Its page on the Planning Portal

Ravensworth Coal MOD 2 - Changes to Final LandformMP09_0176-Mod-2

Decided: approved on 19 Dec 2014 by the department (executive director)

/

Its 10 documents

Its page on the Planning Portal

Mod 1 - Narama West Open CutMP09_0176-Mod-1

Decided: approved with conditions on 16 Aug 2013 by the department (executive director)

Its 13 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.