Decided: approved on 14 Jun 2016Other

Where it is in the process

Approved on 14 Jun 2016

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination14 Jun 2016 (done)
  9. Approved14 Jun 2016

What it proposes

The department's description

Development of a 60 MW solar farm and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

7 submissions: 1 from the public and 6 from organisations

Object0
Support1
Comment6

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Griffith Solar MOD 3 - Griffith SolarSSD-6604-MOD-3

Decided: approved on 5 Jul 2017 by the department (director)

Modification to temporarily allow construction vehicle access on an alternate route, prior to completion of road upgrades on the approved access route.

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

EA4

See the 4 documents on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Griffith Solar MOD 2 - Griffith SolarSSD-6604-MOD-2

Decided: approved on 6 Apr 2017 by the department (director)

Change in a site access point, construction of internal access road and construction of an access way.

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EIS4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Griffith Solar MOD 1 - Griffith SolarSSD-6604-MOD-1

Decided: approved on 25 Oct 2016 by the department (director)

Removal of one site access point and construction of internal access roads.

Its 6 documents

6 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EIS3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.