On the map
State significant development

Forbes Solar Farm

A 166 MW solar farm and battery at Hoopers Road, Forbes

Under way: at assessmentEnergy: solarDistrict scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its EIS Main Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 166 MW solar farm and battery at Hoopers Road, Forbes

The proponent proposes to build, operate and later decommission a 166 MW solar farm at 207 Hoopers Road, Forbes, in the Forbes Shire area. It would include a battery energy storage system with a capacity of 120 MW and 960 MWh, plus ancillary infrastructure. No capital investment, job numbers or site area are stated.

The environmental impact statement (EIS) was prepared in November 2025 and exhibited, drawing 86 submissions: 85 objecting and 1 commenting. The proponent has since responded to submissions, and agencies gave advice on that response. The portal shows the case at the "More Information Required" stage, with a request for additional information listed. Next, the proponent must provide that information. The department then continues its assessment and decides, or refers the decision to the Independent Planning Commission.

Solar farm capacity
166 MWPortal page
Battery power capacity
120 MWPortal page
Battery storage capacity
960 MWhPortal page
Submissions
86 submissionsPortal page
Submissions objecting
85 submissionsPortal page

The department's description

The construction, operation and decommissioning of a 166 MW solar farm, an associated battery energy storage system (BESS) with a capacity 120 MW/960 MWh, and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

86 submissions: 76 from the public and 10 from organisations

Object85
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

60 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs1
EIS18
Response to Submissions2
Agency Advice36
Additional Information1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.