On the map
State significant development

Parkes Energy Recovery Facility

A 732,000 tonne a year energy recovery facility at Parkes

Under way: at exhibitionWasteRegional scale

Where it is in the process

At exhibition, since 5 Nov 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition5 Nov 2026 (current stage)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

Open for comment until 17 Dec 2026. Anyone can make a submission on its page on the Planning Portal.

What it proposes

AI summary. Written from this project's page and its Parkes ERF EIS Main Document on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 732,000 tonne a year energy recovery facility at Parkes

The proponent seeks approval to build and run an energy recovery facility at 545 Nelungaloo Road, Parkes, in the Parkes Special Activation Precinct, in the Parkes Shire. It would process about 732,000 tonnes a year of non-hazardous residual waste, mostly from Greater Sydney and brought by rail, by burning it to make electricity. It would generate 70-80 MW, with about 65 MW exported to the grid. Construction would take about 48 months. The proponent states about 313 ongoing jobs in operation. No capital investment is stated.

The environmental impact statement (EIS) is on exhibition from 5 Nov 2026 to 17 Dec 2026, and no submissions had been recorded. Next, the proponent responds to the submissions, often amending the project. The department then assesses it, with advice from other agencies, and writes an assessment report before a decision is made.

Waste processed
732,000 tonnes a yearParkes ERF EIS Main Document
Electricity generated (upper figure)
80 MWParkes ERF EIS Main Document
Electricity exported to the grid
65 MWParkes ERF EIS Main Document
Construction period
48 monthsParkes ERF EIS Main Document
Ongoing operational jobs
313 jobsParkes ERF EIS Main Document

The department's description

Construction and operation of the Parkes Energy Recovery Facility to receive and process approximately 732,000 tonnes per annum of residual waste for the purpose of energy generation (electricity) via thermal treatment.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

39 documents in 4 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs6
EIS31

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.