Elizabeth Enterprise Precinct - Stage 1
Seven-warehouse industrial estate on Elizabeth Drive, Badgerys Creek
Where it is in the process
Approved on 4 Feb 2026
What it proposes
AI summary. Written from this project's page and its Assessment Report and Development Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Seven-warehouse industrial estate on Elizabeth Drive, Badgerys Creek
The proponent proposed an industrial estate at 1669-1723 Elizabeth Drive, Badgerys Creek, in the Penrith area. The concept proposal covers seven buildings with 139,855 m² of gross floor area and a capital investment of $282 million. Stage 1A, the first stage, covers two buildings of 57,965 m², site-wide earthworks, roads and stormwater, at $132 million. The concept is expected to create up to 309 construction jobs and 1,081 operational jobs. The nearest homes are 60 m south.
The environmental impact statement was exhibited from 2 May 2025 to 29 May 2025. It drew 2 public submissions, both comments, plus one from the council and advice from government authorities. The proponent responded on 13 Oct 2025. The department recommended approval, and its Executive Director approved the project on 4 Feb 2026, with conditions. Each later building needs its own development application. Earthworks cannot start until an alternative stormwater strategy is approved.
- Capital investment (concept)
- $282MAssessment Report
- Stage 1A capital investment
- $132MAssessment Report
- Concept gross floor area
- 139,855 m²Assessment Report
- Stage 1A gross floor area
- 57,965 m²Assessment Report
- Construction jobs (concept)
- 309 jobsAssessment Report
- Operational jobs (concept)
- 1,081 jobsAssessment Report
- Maximum building height
- 16 mAssessment Report
- Distance to nearest homes
- 60 mAssessment Report
The department's description
Concept Masterplan including seven warehouse buildings and internal road network, with a Stage 1 development including bulk earthworks, road construction, construction and fit-out of two warehouse and distribution buildings and associated works
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
4 submissions: 1 from the public, 2 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
2 changes to the project after its decision, each assessed as a case of its own, newest first.
EEP MOD 1 - Concept and Stage 1A AmendmentsSSD-19618251-Mod-1
Modifications to the approved Concept and Stage 1A to redistribute Gross Floor Area, amend levels and retaining walls and change evaporation basin outlet design.
EEP MOD 2 - Amendment to Remediation ConditionsSSD-19618251-Mod-2
Amendment to Remediation Conditions D96 & D100
Its 4 documents
4 documents in 3 folders, each on the NSW Planning Portal
Modification Application1
Determination2
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
193 documents in 12 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs3
EIS62
- 1. Environmental Impact Statement
- A - SEARs Compliance Table
- AA - Smart Cities Requirements
- Application_20250411023603
- B - Architectural Plans
- BB - Landscape Character and Visual Impact Assessment
- C - Statutory Compliance Table
- CC - Mirvac SDRP Response Letter - 1 December 2022
- CC - SDRP Advice Letter - 5 September 2022
- D - Community Engagement Table
- DD - BCA Assessment Report - Warehouse 2
- DD - BCA Assessment Report - Warehouse 6
- E - Consolidated Mitigation Measures
- EE - Fire Safety Strategy - Concept Plan
- EE - Fire Safety Strategy - Stage 1A Development
- F - Aerotropolis DCP Compliance Table
- FF - Transport Assessment
- G - Consultation Outcomes Report
- GG - Geotechnical Investigation Report
- H - EDC Report Final
- HH - Dam Dewatering Management Plan
- I - Design Statement
- II - Flood Impact Assessment
- II - Flood Risk Assessment
- J - Urban Design Report
- K - Civil Drawings
- KK - Noise and Vibration Assessment
- L - Civil Infrastructure Report
- LL - EEP Stage 1 BDAR
- LL - Intersection BDAR
- M - MUSIC Model
- M - Water and Stormwater Management Plan
- MM - Aboriginal Cultural Heritage Assessment Report
- N - Erosion and Sediment Control Plan
- NN - Recognise Country Guidelines
- O - Interim Intersection Design Plans (DA240775)
- OO - Archaeological Research Design Report
- OO - Archaeological Test Excavation Results Report
- OO - Non-Aboriginal Statement of Heritage Impact
- OO - Salvage Excavation ARD Report
- P - Plan of Subdivision
- PP - Social Impact Assessment
- Q - Landscape Report
- QQ - Preliminary Site Investigation
- R - Landscape Drawings - Site Wide Infrastructure
- R - Landscape Drawings - Warehouse 2
- R - Landscape Drawings - Warehouse 6
- RR - Detailed Site Investigation - Stage 1
- RR - Detailed Site Investigation - Stage 2
- S - Net Zero Statement
- SS - Remedial Action Plan
- T - ESD Report
- TT - Bushfire Assessment Report
- U - Aeronautical Impact Assessment
- UU - Air Quality Impact Assessment
- V - Wildlife Hazard Assessment
- VV - Waste Management Plan
- W - Agreement to Rate (Warehouse 2)
- W - Agreement to Rate (Warehouse 6)
- X - Consistency with AIE Memorandum
- Y - Connecting with Country Framework (Pub Exh)
- Z - Public Art Strategy
Response to Submissions39
- A - Submissions Register
- AA - Fire Safety Strategy Concept Plan
- AA - Fire Safety Strategy Stage 1A
- B - Updated Mitigation Measures
- BB - BCA Assessment Report - WH2
- BB - BCA Assessment Report - WH6
- C - Updated Architectural Masterplan Dwgs Sep 2025
- C - Updated Lot 2 Architectural Plans Sep 2025
- C - Updated Lot 6 Architectural Plans Sep 2025
- CC - Vegetation Management Plan
- D - Updated Design Statement
- DD - Groundwater Seepage Analysis
- E - Updated Landscape Report Sep 2025
- EE - Consistency Memo with AIE
- F - Updated Warehouse 2 Landscape Plans
- G - Updated Warehouse 6 Landscape Plans
- H - Updated Site Wide Infrastructure Landscape Plans
- I - Updated Connecting with Country Framework
- J - Transport Assessment Addendum
- J - Transport Assessment Addendum - Swept Paths
- K - Flood Impact Assessment Addendum
- L - Updated Landscape Character VIA
- M - Updated Air Quality Impact Assessment Sep 2025
- N - Updated BDAR
- O - Updated ACHAR Amendment
- O - Updated ACHAR Appendix E - Consultation Records
- P - Updated Archaological Research Design
- Q - Updated Statement of Heritage Impact
- R - Updated ESD Report
- Request RTS 2 June 2025
- S - Updated Waste Management Plan
- Submissions Report - EEP Stage 1
- T - Updated Dam Dewatering Plan
- U - Updated Aeronautical Impact Assessment
- V - Updated Bushfire Hazard Assessment Sep 2025
- W - Updated Civil Drawings
- X - Updated Civil Infrastructure Report Sep 2025
- Y - Updated WSMP
- Z - Updated Erosion and Sediment Control Plan Sep 2025
Agency Advice51
- Advice on Additional Info - CPHR
- Advice on Additional Info - DCCEEW Water
- Advice on Additional Info - Fire & Rescue NSW
- Advice on Additional Info - Penrith Council
- Advice on Additional Info - Sydney Water
- Advice on Additional Info - Sydney Water attmt
- Advice on RTS - CPHR
- Advice on RTS - DCCEEW Water
- Advice on RTS - FRNSW
- Advice on RTS - Heritage Council NSW
- Advice on RTS - Heritage NSW ACH
- Advice on RTS - Penrith Council
- Advice on RTS - Rural Fire Service
- Advice on RTS - Sydney Water
- Advice on RTS - TfNSW
- Advice on RTS - Western Syd International Airport
- EIS Advice - CPHR
- EIS Advice - Crown Lands
- EIS Advice - DCCEEW Water
- EIS Advice - Fire and Rescue NSW
- EIS Advice - Heritage NSW Aboriginal Cultural Heritage
- EIS Advice - Heritage NSW Heritage Council
- EIS Advice - Penrith Council
- EIS Advice - Rural Fire Service
- EIS Advice - Sydney Water
- EIS Advice - Transport for NSW
- EIS Advice - Water NSW
- EIS Advice - Western Sydney Airport
- SEARS Advice - Sydney Water
- SEARs Advice - Crown Lands
- SEARs Advice - DPIE Water
- SEARs Advice - EE Attachment 1
- SEARs Advice - EE Attachment 10
- SEARs Advice - EE Attachment 11
- SEARs Advice - EE Attachment 2
- SEARs Advice - EE Attachment 3
- SEARs Advice - EE Attachment 4
- SEARs Advice - EE Attachment 5
- SEARs Advice - EE Attachment 6
- SEARs Advice - EE Attachment 7
- SEARs Advice - EE Attachment 8
- SEARs Advice - EE Attachment 9
- SEARs Advice - EES
- SEARs Advice - EPA
- SEARs Advice - Endeavour Energy
- SEARs Advice - Heritage NSW
- SEARs Advice - Penrith City Council
- SEARs Advice - TfNSW
- SEARs Advice - WSPP
- SEARs Advice - WaterNSW
- SEARs Advice - Western Sydney Airport
Additional Information13
- 9 December 2025 Response to RFI
- A - Updated Stage 1 Masterplan
- B - Updated Civil Infrastructure Report
- B - Updated Civil Plans
- C - Updated Water and Stormwater Management Plan
- D - Updated Erosion and Sediment Control Plan
- E - Updated Civil Infrastructure Plans
- F - Groundwater Seepage Analysis
- G - Geotechnical Analysis
- H - Updated Landscape Report
- I - Updated Landscape Infrastructure Plans
- MUSIC Modelling
- RFI - Design Response 12 May 2025
Determination3
Management Plans and Strategies3
Reports6
Independent Reviews and Audits7
What's near it
Where it is
- Suburb
- Badgerys Creek
- Council area
- Penrith
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.