On the map
State significant development

Eastern Creek Data Centre Expansion Project

Decided: approved on 1 Sep 2023Industry and warehouses

Where it is in the process

Approved on 1 Sep 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination1 Sep 2023 (done)
  9. Approved1 Sep 2023

What it proposes

The department's description

An expansion to an existing data centre, including associated office space, supporting infrastructure and services, car parking and landscaping.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

4 submissions: 3 from organisations and 1 from public authorities

Object2
Support0
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Eastern Creek Data Centre - Mod 2 - Power consumption increaseSSD-21342738-Mod-2

Decided: approved on 5 Aug 2026 by the department (team leader)

The modification seeks approval for an increase in the overall power consumption of the development (to 70.2 megawatts), along with corresponding plant and equipment changes (including additional back-up generators).

Its 52 documents

52 documents in 5 folders, each on the NSW Planning Portal

Modification Application19

See the 19 documents on the Planning Portal

Agency Advice10

See the 10 documents on the Planning Portal

Additional Information18

See the 18 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Eastern Creek DC Expansion Project MOD 1 - WaterSSD-21342738-Mod-1

Decided: approved on 18 Sep 2025 by the department (team leader)

Re-arrangement of approved water storages and car parking spaces

Its 12 documents

12 documents in 3 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.