On the map
State significant development

Honeman Close Data Centre

A 96 MW data centre at 6 Honeman Close, Huntingwood

Decided: approved on 1 Oct 2026Data centresRegional scale

Where it is in the process

Approved on 1 Oct 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination1 Oct 2026 (done)
  9. Approved1 Oct 2026

What it proposes

AI summary. Written from this project's page and its SSD-58601963 - Assessment Report and SSD-58601963 - Development Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 96 MW data centre at 6 Honeman Close, Huntingwood

The project is a data centre with an information technology load of 96 MW at 6 Honeman Close, Huntingwood, in the Blacktown council area. It would be a 43 m high building with 40 data halls on a site of about 5.03 ha. The department gives a capital investment of $1,263,226,278, with up to 250 construction jobs and 74 operational jobs. It would be backed up by 44 diesel generators of 3 MW each.

The environmental impact statement was exhibited from 14 Dec 2023 to 1 Feb 2024 and drew 12 submissions: 2 objecting and 10 commenting. The proponent responded and gave more information. The department's assessment focused on noise, air quality, biodiversity and urban design. A director of the department, as the Minister's delegate, approved it on 1 Oct 2026, with conditions. Next, the proponent must meet those conditions, including a limit of 187 hours a year of generator use.

Capital investment
$1.26bnSSD-58601963 - Assessment Report
IT load
96 MWSSD-58601963 - Assessment Report
Construction jobs
250 jobsSSD-58601963 - Assessment Report
Operational jobs
74 jobsSSD-58601963 - Assessment Report
Site area
5.03 haSSD-58601963 - Assessment Report
Data halls
40 data hallsSSD-58601963 - Assessment Report
Maximum generator operation
187 hours a yearSSD-58601963 - Development Consent

The department's description

Construction and operation of a new 96MW data centre with associated civil works.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

12 submissions: 1 from the public, 2 from organisations and 9 from public authorities

Object2
Support0
Comment10

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

111 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition1
Early Consultation2
Request for SEARs1
SEARs1
EIS37
Response to Submissions27
Agency Advice9
Additional Information28
Determination5

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.