Decided: approved on 17 Nov 2010Mixed use

Where it is in the process

Approved on 17 Nov 2010

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination17 Nov 2010 (done)
  10. Approved17 Nov 2010

What it proposes

The portal gives no description.

Modifications

6 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 6 - Car Parking ChangesMP09_0041-Mod-6

Decided: approved on 23 Dec 2016 by the department (executive director) · 1 submission

Its 9 documents

Its page on the Planning Portal

Mod 5 - Administrative ChangesMP09_0041-Mod-5

Decided: approved on 11 Jul 2013 by the department (executive director)

Its 9 documents

Its page on the Planning Portal

Mod 4 - Construction Hours & WorksMP09_0041-Mod-4

Decided: approved on 3 Dec 2012 by the department (deputy director-general)

Its 11 documents

11 documents in 3 folders, each on the NSW Planning Portal

Application9

See the 9 documents on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 3 - Further Design ChangesMP09_0041-Mod-3

Decided: approved on 21 Aug 2012 by the department (deputy director-general)

Its 22 documents

22 documents in 2 folders, each on the NSW Planning Portal

Application21

See the 21 documents on the Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 2 - Energy Star Ratings ConditionMP09_0041-Mod-2

Decided: approved on 31 Jul 2012 by the department (deputy secretary)

Its page on the Planning Portal

Mod 1 - Design ChangesMP09_0041-Mod-1

Decided: approved on 22 Dec 2011 by the department (deputy director-general)

Its 99 documents

99 documents in 3 folders, each on the NSW Planning Portal

Application65

See the 65 documents on the Planning Portal

EA32

See the 32 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.