Cardboard factory fit-out at 200 Aldington Road, Kemps Creek
Where it is in the process
Approved on 16 Apr 2026
What it proposes
AI summary. Written from this project's page and its SSD-79300218 Assessment Report and SSD-79300218 Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Cardboard factory fit-out at 200 Aldington Road, Kemps Creek
The project changes the use of Warehouse 5 (Lot F) in the 200 Aldington Road Industrial Estate, Kemps Creek, in the Penrith area, to general industry. It fits out the building to make and distribute cardboard products, with offices and staff amenities. It would make about 84,000 tonnes of finished cardboard products a year and run 24 hours a day, 7 days a week. The department's report gives a development cost of $52.3 million, 183 construction jobs and 250 operational jobs. About 995 vehicles a day are expected. The external building design is unchanged.
The environmental impact statement (EIS) was exhibited from 8 May 2025 to 4 Jun 2025. The 2 submissions on the portal page were comments, from an organisation and a public authority. The department recommended approval, and a director of the department, as the Minister's delegate, approved it on 16 Apr 2026, with conditions. Next, the proponent must meet those conditions before construction and operation.
- Capital investment
- $52.3MSSD-79300218 Assessment Report
- Construction jobs
- 183 jobsSSD-79300218 Assessment Report
- Operational jobs
- 250 jobsSSD-79300218 Assessment Report
- Annual production capacity
- 84,000 tonnes a yearSSD-79300218 Assessment Report
- Vehicles a day
- 995 vehiclesSSD-79300218 Assessment Report
- Car spaces
- 250 car spacesSSD-79300218 Assessment Report
- Lot F gross floor area
- 51,027 m²SSD-79300218 Assessment Report
- Site area
- 78,420 m²SSD-79300218 Assessment Report
The department's description
Fit out and use of the Stage 1 building on Lot F in the 200 Aldington Road Industrial Estate for the purposes of manufacturing and distribution of cardboard packaging.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
2 submissions: 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
66 documents in 8 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
EIS25
- Appendix A - SEARs Compliance Table
- Appendix B - Architectural Drawing
- Appendix C - Statutory Compliance Table
- Appendix D - Consolidated Mitigation Measures
- Appendix E - Response to Government Agencies Comments
- Appendix F- Aboriginal and Historical Heritage Letter
- Appendix G - Air Quality Impact Assessment
- Appendix H - Aviation Statement
- Appendix I - BCA Assessment Report
- Appendix J - Bushfire Statement
- Appendix K - Construction Environmental Management Plan
- Appendix L - MRP DCP Assessment
- Appendix M - Waste Management Plan
- Appendix N - Transport Impact Assessment
- Appendix O - Community & Stakeholder Engagement
- Appendix P - Hazardous Screening Assessment
- Appendix Q - Sustainability Report
- Appendix R - Embodied Emissions Materials Form
- Appendix S- Fire Safety Statement
- Appendix T - Noise Impact Assessment
- Appendix U - Social Impact Assessment Addendum
- Appendix V - Sydney Water Growth Form
- Application_20250417053742
- EDC Report
- Environmental Impact Statement - SSD-79300218
Response to Submissions14
- Appendix C - Updated Traffic Impact Assessment
- Appendix D - Updated Noise Impact Assessment
- Appendix E - Updated Waste Management Plan
- Appendix F - Utilities Infrastructure Statement
- Appendix G - Ground Floor Layout Plan
- Appendix H - Operational Layout Plan
- Appendix I - Updated Air Quality Impact Statement
- Appendix J - Greenhouse Gas Assessment
- Appendix K - Process Flow Diagram
- Appendix L - Correspondance with RAPs
- Department's RtS Comments
- Request for Additional Information
- SSD-79300218 Request RTS Letter
- Submissions Report-200 Aldington Road Lot F
Agency Advice17
Management Plans and Strategies3
What's near it
Where it is
- Suburb
- Kemps Creek
- Council area
- Penrith
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.