On the map
State significant development

Cardboard Manufacturing - 200 Aldington Road Lot F

Cardboard factory fit-out at 200 Aldington Road, Kemps Creek

Decided: approved on 16 Apr 2026Industry and warehousesNeighbourhood scale

Where it is in the process

Approved on 16 Apr 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination16 Apr 2026 (done)
  9. Approved16 Apr 2026

What it proposes

AI summary. Written from this project's page and its SSD-79300218 Assessment Report and SSD-79300218 Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Cardboard factory fit-out at 200 Aldington Road, Kemps Creek

The project changes the use of Warehouse 5 (Lot F) in the 200 Aldington Road Industrial Estate, Kemps Creek, in the Penrith area, to general industry. It fits out the building to make and distribute cardboard products, with offices and staff amenities. It would make about 84,000 tonnes of finished cardboard products a year and run 24 hours a day, 7 days a week. The department's report gives a development cost of $52.3 million, 183 construction jobs and 250 operational jobs. About 995 vehicles a day are expected. The external building design is unchanged.

The environmental impact statement (EIS) was exhibited from 8 May 2025 to 4 Jun 2025. The 2 submissions on the portal page were comments, from an organisation and a public authority. The department recommended approval, and a director of the department, as the Minister's delegate, approved it on 16 Apr 2026, with conditions. Next, the proponent must meet those conditions before construction and operation.

Capital investment
$52.3MSSD-79300218 Assessment Report
Construction jobs
183 jobsSSD-79300218 Assessment Report
Operational jobs
250 jobsSSD-79300218 Assessment Report
Annual production capacity
84,000 tonnes a yearSSD-79300218 Assessment Report
Vehicles a day
995 vehiclesSSD-79300218 Assessment Report
Car spaces
250 car spacesSSD-79300218 Assessment Report
Lot F gross floor area
51,027 m²SSD-79300218 Assessment Report
Site area
78,420 m²SSD-79300218 Assessment Report

The department's description

Fit out and use of the Stage 1 building on Lot F in the 200 Aldington Road Industrial Estate for the purposes of manufacturing and distribution of cardboard packaging.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

2 submissions: 1 from organisations and 1 from public authorities

Object0
Support0
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

66 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs2
EIS25
Response to Submissions14
Agency Advice17
Determination3
Management Plans and Strategies3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.