On the map
Part 4 development

Boral Material Recycling Facility

Decided: approved on 25 Nov 2002Waste

Where it is in the process

Approved on 25 Nov 2002

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination25 Nov 2002 (done)
  10. Approved25 Nov 2002

What it proposes

The portal gives no description.

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Capacity IncreaseDA21-1-2002-I-Mod-1

Decided: approved by the department (director)

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

2 documents in 1 folder, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.