On the map
State significant development

Bendemeer Wind Farm

A 51-turbine wind farm east of Bendemeer

Under way: at prepare eisEnergy: windDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 51-turbine wind farm east of Bendemeer

The proponent proposes a wind farm of up to 51 wind turbines with a generation capacity of up to 316 MW, east of Bendemeer in the Tamworth Regional Council area. Each turbine would stand up to 250 m to its blade tip. The project area covers 9,072.5 ha on land mostly used for farming. It includes up to four substations and a connection to the existing 330 kV Armidale-Tamworth transmission line. The scoping report estimates a capital investment of about $750 million. It is the second stage of a larger renewable energy hub, alongside a separately assessed solar farm.

The scoping report is dated 15 Nov 2024. The Secretary's environmental assessment requirements (SEARs) have been issued, and agencies have given advice on them. The proponent is now preparing an environmental impact statement (EIS). When it is lodged, it is to be exhibited and the public can make submissions. No submissions have been made yet.

Capital investment
$750MScoping Report
Wind turbines
51 turbinesScoping Report
Generation capacity
316 MWScoping Report
Maximum turbine tip height
250 mScoping Report
Project area
9,072.5 haScoping Report

The department's description

Construction and operation of a wind farm with up to 51 wind turbines and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.