On the map
State significant development

Barangaroo - Crown Hotel Resort

Decided: approved on 28 Jun 2016Commercial and retail

Where it is in the process

Approved on 28 Jun 2016

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination28 Jun 2016 (done)
  8. Approved28 Jun 2016

What it proposes

The portal gives no description.

Submissions

What the public, organisations and public authorities said, counted by where they stood.

54 submissions: 21 from the public and 33 from organisations

Object27
Support6
Comment21

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

11 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 8 - Window ChangesSSD-6957-Mod-8

Under way: at prepare mod report

Installation of operable terrace windows and landscaping to the ground floor al-fresco dining areas.

Its page on the Planning Portal

MOD 11 - Installation of Roof Building Maintenance UnitSSD-6957-Mod-11

Under way: at assessment

Provision of a Building Maintenance Unit (BMU) on the roof of the approved Crown Hotel building.

Its 8 documents

8 documents in 2 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Its page on the Planning Portal

Modification 10 - Rooftop Bar Canopy AdditionSSD-6957-Mod-10

Decided: approved on 2 Jul 2026 by the department (executive director)

Works to level 26 rooftop bar to add a canopy and relocate a door.

Its 8 documents

8 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Barangaroo Crown Hotel Resort MOD 9 - Trial PeriodSSD-6957-Mod-9

Decided: approved on 26 Feb 2025 by the department (executive director)

Continuation of current trial period hours for the restaurants and bars (not associated with gaming areas)

Its 6 documents

6 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Barangaroo Crown Hotel Resort MOD 7 - HoursSSD-6957-Mod-7

Decided: approved on 9 Feb 2022 by the department (executive director)

Extension to the duration of the trial period operating hours of the restaurants, bars (not associated with gaming areas) and Ground Floor outdoor seating areas.

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Barangaroo Crown Hotel Resort MOD 6 - AlterationsSSD-6957-Mod-6

Decided: approved on 10 Dec 2021 by the department (executive director)

Additional cabana spaces at Level 4 and alterations to Ground Floor western terrace area, including additional glass blades, landscaping and consolidation of entry points to dining areas.

Its 11 documents

11 documents in 4 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Barangaroo Crown Hotel Resort MOD 5 - StagingSSD-6957-Mod-5

Decided: approved on 2 Nov 2020 by the department (director)

Section 4.55 (1A) application to facilitate the staged delivery of Hickson Park.

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Barangaroo Crown Hotel Resort MOD 4 - SignageSSD-6957-Mod-4

Decided: approved on 21 Oct 2020 by the department (director)

New kitchen & staff room, additional PV arrays at Level 4 and 5 terrace roofs, expansion of Level 64 residential terrace to accommodate a pool, raising of roof level parapet glazing, 2 new business identification signage zones, minor changes to GFA

Its 26 documents

26 documents in 5 folders, each on the NSW Planning Portal

Modification Application13

See the 13 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information8

See the 8 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Barangaroo Crown Hotel Resort MOD 3 - LayoutSSD-6957-Mod-3

Decided: approved on 13 Jul 2020 by the department (executive director)

Amalgamation of apartments on levels 48 and 49

Its 16 documents

16 documents in 4 folders, each on the NSW Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Barangaroo Crown Hotel Resort MOD 2 - DesignSSD-6957-Mod-2

Decided: approved on 7 May 2020 by the department (executive director)

Internal design changes, including amalgamating and consolidating apartments

Its 16 documents

16 documents in 4 folders, each on the NSW Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information6

See the 6 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Barangaroo Crown Hotel Resort MOD 1 - DesignSSD-6957-Mod-1

Decided: approved on 31 Oct 2019 by the department (deputy secretary) · 11 submissions

Reconfiguration of the internal layout of the hotel, retail and tourism uses; 21 additional apartments; design changes to car park, ground level, levels 3, 4, 24 and 66. No change is sought to the approved 77,500 GFA of the building.

Its 62 documents

62 documents in 4 folders, each on the NSW Planning Portal

Modification Application38

See the 38 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information17

See the 17 documents on the Planning Portal

Determination5

See the 5 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.