On the map
State significant development

Armidale East Battery Energy Storage System

A 377 MW battery at 315 Bayley Park Road, Metz

Under way: at response to submissionsEnergy: batteriesDistrict scale

Where it is in the process

At response to submissions

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (current stage)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 377 MW battery at 315 Bayley Park Road, Metz

The proponent proposes to build, operate and later decommission a battery energy storage system at 315 Bayley Park Road, Metz, in the Armidale Regional Council area. It would have a capacity of up to 377 MW and 2,310 MWh, with ancillary infrastructure. The environmental impact statement (EIS) describes a battery compound, a substation and switchyard, access roads and road upgrades, and a proposed subdivision. No capital investment or job numbers are stated.

The EIS (final version dated 11 Sep 2026) was exhibited and drew 6 submissions: 4 objecting and 2 supporting. The case is at the response to submissions stage, where the proponent replies to the issues raised and may amend the project. The department then assesses it, with advice from other agencies, and writes an assessment report before a decision is made.

Battery power capacity
377 MWPortal page
Battery storage capacity
2,310 MWhPortal page
Public submissions
6 submissionsPortal page

The department's description

The construction, operation and decommissioning of a battery energy storage system with a capacity of up to 377 MW / 2,310 MWh, and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

6 submissions: 5 from the public and 1 from organisations

Object4
Support2
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

53 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs6
SEARs2
EPBC1
EIS14
Response to Submissions1
Agency Advice28

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.