On the map
State significant development

Oxley Solar Farm

Decided: approved on 11 Dec 2023Energy: solarDistrict scale

Where it is in the process

Approved on 11 Dec 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination11 Dec 2023 (done)
  9. Approved11 Dec 2023

What it proposes

The department's description

Development of a 215 MW solar farm with up to 50 MW of battery energy storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

95 submissions: 78 from the public, 1 from organisations and 16 from public authorities

Object78
Support0
Comment17

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.