On the map
State significant development

Wyong Hospital Expansion

Decided: approved on 29 Aug 2019Health

Where it is in the process

Approved on 29 Aug 2019

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination29 Aug 2019 (done)
  9. Approved29 Aug 2019

What it proposes

The department's description

Construction of a six storey Clinical Services Building (CSB), including an under-croft carpark, podium, Emergency Department, Psychiatric Emergency Centre, Intensive Care Unit, Paediatrics, In Patient Units and an Acute Medical Unit.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

12 submissions: 1 from the public and 11 from organisations

Object1
Support0
Comment11

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Wyong Hospital Expansion MOD 2 - Design changesSSD-9536-Mod-2

Decided: approved on 15 Jul 2021 by the department (team leader)

Internal and external building design refinements and changes to the landscaping design of the Wyong Hospital Expansion project.

Its 13 documents

13 documents in 3 folders, each on the NSW Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Wyong Hospital Expansion MOD 1 - Admin correctionsSSD-9536-Mod-1

Decided: approved on 17 Oct 2019 by the department (director)

Correction of minor errors and misdescription in development consent.

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.