State significant development

White Rock Solar Farm

Decided: approved on 14 Jun 2016Other

Where it is in the process

Approved on 14 Jun 2016

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination14 Jun 2016 (done)
  8. Approved14 Jun 2016

What it proposes

The department's description

Development of a 20 MW solar farm and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

8 submissions: 1 from the public and 7 from organisations

Object0
Support0
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

White Rock Solar MOD 1 - Site Layout ChangesSSD-7487-MOD-1

Decided: approved on 21 Dec 2017 by the department (director)

Changes to site layout to include to include a temporary car park and to amend the route of the approved underground transmission cable

Its 5 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.