State significant development

Sundown Solar Farm

Decided: approved on 4 Aug 2026Energy: solarDistrict scale

Where it is in the process

Approved on 4 Aug 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination4 Aug 2026 (done)
  9. Approved4 Aug 2026

What it proposes

The department's description

Development of a 360 MW solar farm with energy storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

144 submissions: 136 from the public, 7 from organisations and 1 from public authorities

Object134
Support5
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

86 documents in 8 folders, each on the NSW Planning Portal

Request for SEARs1
SEARs3
EIS15
Response to Submissions18
Agency Advice37
Additional Information7
Determination2
Recommendation3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.