Westlink Industrial Estate - Stage 1

Decided: approved on 21 Apr 2023Industry and warehouses

Where it is in the process

Approved on 21 Apr 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination21 Apr 2023 (done)
  9. Approved21 Apr 2023

What it proposes

The department's description

Construction of 2 warehouse buildings and ancillary office space, bulk earthworks and vegetation clearing, construction of roads and external road upgrades, site servicing and stormwater infrastructure, landscaping and subdivision.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

15 submissions: 3 from the public, 2 from organisations and 10 from public authorities

Object0
Support1
Comment14

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

7 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 1 - Bulk Earthworks Fill LocationSSD-9138102-Mod-1

Withdrawn: withdrawn

Proposal to amend the approved bulk earthworks to enable excess fill from the excavation for Lot 1 (Warehouse 1) and Lot 4 (Warehouse 4) building pads to be used for the filling of the future Lot 6.

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.