  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination20 Jun 2007 (done)
  10. Approved20 Jun 2007

What it proposes

The portal gives no description.

Modifications

8 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 8 - Management Plan RequirementsMP06_0190-Mod-8

Decided: approved on 21 Nov 2017 by the department (director)

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Application6

See the 6 documents on the Planning Portal

Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 7 - Noise RequirementsMP06_0190-Mod-7

Decided: approved on 1 Apr 2011 by Dir(MIA)

Its 5 documents

5 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 6 - Further Biodiversity ImpactsMP06_0190-Mod-6

Decided: approved on 15 Jul 2009 by the department (executive director)

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 5 - Further Tree RemovalMP06_0190-Mod-5

Decided: approved on 20 Mar 2009 by the department (director-general)

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

EA1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 4 - Tree RemovalMP06_0190-Mod-4

Decided: approved on 22 Dec 2008 by the department (executive director)

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 3 - Biodiversity ImpactsMP06_0190-Mod-3

Decided: approved on 3 Nov 2008 by the department (executive director)

Modification 3 to the Western Sydney Water Recycling Facility, dealing with biodiversity impacts near Quakers Hill, approved by the department on 3 Nov 2008.

Its 5 documents

Its page on the Planning Portal

Mod 2 - Biological MonitoringMP06_0190-Mod-2

Decided: approved on 17 Oct 2008 by the department (executive director)

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 1 - Flora and FaunaMP06_0190-Mod-1

Decided: approved on 10 Jun 2008 by the department (executive director)

Its 6 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

8 documents in 4 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

EA1

See the document on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.