On the map
State significant development

Wanganella Wind Farm

An 840 MW wind farm and battery at Wanganella

Under way: at prepare eisEnergy: windRegional scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

An 840 MW wind farm and battery at Wanganella

The proponent proposes a wind farm at Wanganella, north of the town and east of the Cobb Highway, in the Edward River Council area. It would have up to 105 turbines with a capacity of 840 MW, each up to 270 m high to the blade tip. It also includes a 600 MW / 2,400 MWh battery, a substation and temporary worker accommodation. The site covers about 30,737 ha, and the area actually disturbed is estimated at about 1,537 ha. No capital investment or job numbers are stated.

The proponent's scoping report is dated 21 Nov 2024, and the Secretary's environmental assessment requirements (SEARs) have been issued. The proponent is now preparing an environmental impact statement (EIS), so no decision has been made and no public submissions have been received. Next, the EIS is to be exhibited for public submissions, then the department assesses the project.

Wind farm capacity
840 MWPortal page
Maximum number of turbines
105 turbinesPortal page
Maximum turbine height
270 mPortal page
Battery power capacity
600 MWPortal page
Battery storage capacity
2,400 MWhPortal page
Site area
30,737 haScoping Report
Estimated disturbance area
1,537 haScoping Report

The department's description

Construction, operation and decommissioning of a wind farm with an estimated capacity of 840 MW, up to 105 turbines and a maximum height of 270m (to blade tip), a 600 MW / 2400 MWh BESS, and temporary worker accommodation

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Where it is

Suburb
Wanganella
Council area
Edward River

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Other State projects near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.