Decided: approved on 17 May 2018Tourism and recreation

Where it is in the process

Approved on 17 May 2018

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination17 May 2018 (done)
  8. Approved17 May 2018

What it proposes

The department's description

Walsh Bay Arts & Cultural Precinct

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

57 submissions: 43 from the public and 14 from organisations

Object32
Support15
Comment10

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

7 changes to the project after its decision, each assessed as a case of its own, newest first.

Walsh Bay - Modification 2 Extension of construction hoursSSD-8671-Mod-2

Under way: at assessment

Extension of construction hours on Saturdays from 1 pm to 5 pm. Internal works only. No external works are proposed during the extended hours.

Its 8 documents

8 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Submissions2

See the 2 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Its page on the Planning Portal

Walsh Bay Arts & Cultural Precinct MOD 7 - LayoutSSD-8671-Mod-7

Decided: approved on 8 Mar 2022 by the department (team leader)

The proposal seeks to extend uses for commercial tenancies 2-4 in Shore Shed 4/5 and the installation of additional louvres to Wharf 4/5.

Its 13 documents

13 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information6

See the 6 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Walsh Bay Arts & Cultural Precinct MOD 6 - DesignSSD-8671-Mod-6

Decided: approved on 2 Dec 2021 by the department (team leader)

The modification seeks the addition of: - a roller door in place of the existing gantry doors - a glass panel on the stairs along the eastern side of Pier 2/3

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Walsh Bay Arts & Cultural Precinct MOD 5 - DesignSSD-8671-Mod-5

Decided: approved on 10 Nov 2021 by the department (team leader)

The modification seeks : - additional louvres - removal of a roof-pop at the northern end of the pier - reduction in the extent of perforated roof sheeting over plant areas - revised plant design and location of lift 3.

Its 15 documents

15 documents in 5 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Walsh Bay Arts & Cultural Precinct MOD 4 - SeatingSSD-8671-Mod-4

Decided: approved on 23 Dec 2020 by the department (director)

The modification seeks to amend condition E36 as it relates to the timing of provision of information to the Secretary to allow progressive occupation of tenancies.

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Walsh Bay Arts & Cultural Precinct MOD 3 - DesignSSD-8671-Mod-3

Decided: approved on 10 Sep 2020 by the department (director)

Proposed changes to the roof ventilation, installation of safety barriers along the apron, expansion of commercial tenancy 3 and expansion of windows at the northern end of Wharf 4/5.

Its 9 documents

9 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Walsh Bay Arts Precinct - Mod 1 - Fire ServicesSSD-8671-Mod-1

Decided: approved on 28 Mar 2019 by the department (director)

Section 4.55(1A) modification application relating to the timing of fire strategies.

Its 2 documents

2 documents in 1 folder, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.