State significant development

Wagga Wagga Quarry

Decided: approved on 22 Nov 2011Quarries

Where it is in the process

Approved on 22 Nov 2011

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination22 Nov 2011 (done)
  8. Approved22 Nov 2011

What it proposes

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Wagga Wagga Quarry Mod 2 - Cell 2/3 boundary regularisationMP07_0069-Mod-2

Under way: at assessment · 2 submissions

Expansion of the Cell 2/3 extraction boundary to incorporate an area identified as having been extracted beyond the approved boundary following a compliance investigation.

Its 10 documents

10 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Its page on the Planning Portal

Wagga Wagga Quarry MOD 1 - Truck HoursMP07_0069-Mod-1

Decided: approved on 30 Oct 2018 by the department (director)

/

Its 10 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.