UNSW Building E25 Biolink
Where it is in the process
Approved on 16 Dec 2025
What it proposes
The department's description
Partial demolition of the UNSW E25 Biolink building, earthworks, extension of the existing building, internal upgrades and facade works.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
2 submissions: 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
UNSW E25 Mod-1 - Building E25 minor design changesSSD-73456206-Mod-1
Minor internal and external design refinements including new rooftop flues.
Its 26 documents
26 documents in 6 folders, each on the NSW Planning Portal
Modification Application15
Agency Advice3
Amendments2
Additional Information2
Determination3
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
71 documents in 11 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs2
SEARs2
EIS35
- Appendix A - SEARs Table.
- Appendix AA - Social Impact Assessment.
- Appendix B - List of Documents & Drawings.
- Appendix BB - Traffic Impact Assessment.
- Appendix C - Statutory Compliance Table.
- Appendix CC - CPTED Report.
- Appendix D - Mitigation Measures.
- Appendix DD - Environmental Wind Assessment Report.
- Appendix E - Engagement Outcomes Report.
- Appendix EE - Fire Safety Engineering Statement.
- Appendix F - Architectural Design Report.
- Appendix FF - BDAR Waiver.
- Appendix G - Connecting with Country Report.
- Appendix GG - Architectural Plans.
- Appendix H - Landscape Plans.
- Appendix HH - Embodied Emissions Materials Form
- Appendix J - BCA Report.
- Appendix K - Accessibility Report.
- Appendix L - ESD Report and Net Zero Statement.
- Appendix M - Survey Plan.
- Appendix N - Preliminary Risk Screening.
- Appendix O - Geotechnical Investigation.
- Appendix P - Preliminary Site Investigation.
- Appendix Q - Groundwater Impact Assessment.
- Appendix R - Noise and Vibration Impact Assessment.
- Appendix S - Infrastructure Report.
- Appendix T - Hazardous Materials Survey
- Appendix U - Integrated Water Management Plan.
- Appendix V - Aboriginal Cultural Heritage Assessment.
- Appendix W - Civil Engineering Plans.
- Appendix X - Aviation Impact Assessment.
- Appendix Y - Waste Management Plan.
- Appendix Z - Flood Risk and Impact Assessment.
- Application_20250324000058
- Environmental Impact Statement
Response to Submissions9
- Appendix A - Updated Architectural Plans
- Appendix B - Updated Architectural Design Report
- Appendix C -Updated Noise & Vibration Assessment
- Appendix D - Flood Risk and Impact Assessment
- Appendix E - Updated ESD Report
- Appendix F - ACHAR Addendum
- Appendix G - Landscape Plans
- Request RtS Letter
- Response to Submissions (RtS) Report
Additional Information7
Determination4
Management Plans and Strategies1
Notifications2
Other Documents1
What's near it
Where it is
- Suburb
- Kensington
- Council area
- Randwick
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.