Ulan Coal Mine - Expansion
Where it is in the process
Approved on 15 Nov 2010
What it proposes
The portal gives no description.
Modifications
9 changes to the project after its decision, each assessed as a case of its own, newest first.
Mod 9 - Proposed Infrastructure RealignmentMP08_0184-Mod-9
Amendment of the location of surface infrastructure approved under Mod 6
Its 1 documents
1 document in 1 folder, each on the NSW Planning Portal
Early Consultation1
Mod 8 - Ulan West Continued Operations.MP08_0184-Mod-8
Extension of the existing underground mine to the west of the approved underground operations including extension to existing longwall panels and addition of four new longwall panels. The modification would extract an addition 38Mt of product coal.
Its 47 documents
47 documents in 7 folders, each on the NSW Planning Portal
Early Consultation1
Notice of Exhibition1
Modification Application22
Response to Submissions2
Agency Advice18
Additional Information2
Ulan Coal Mod 6 - underground mining extensionMP08_0184-Mod-6
ALL DOCUMENTS REGARDING THE SECOND AMENDMENT ARE AVAILABLE IN THE "AMENDMENTS' FOLDER BEGINNING WITH THE TITLE "SECOND AMENDMENT - THESE ARE THE SUBJECT OF THE 2ND EXHIBITION OF THE MODIFICATION APPLICATION
Its 87 documents
87 documents in 10 folders, each on the NSW Planning Portal
Early Consultation1
Notice of Exhibition2
Modification Application18
Response to Submissions7
Agency Advice25
Amendments19
Additional Information8
Determination4
Consolidated Consent1
MOD 7 - Alternative Offset SiteMP08_0184-Mod-7
Modification seeking approval for an alternative biodiversity offset site.
Its 10 documents
10 documents in 3 folders, each on the NSW Planning Portal
Modification Application7
Determination2
Consolidated Consent1
MOD 5 - Administrative modification to correct misdescriptionMP08_0184-Mod-5
Administrative modification to amend an error in figures included in the Project Approval
Its 4 documents
4 documents in 3 folders, each on the NSW Planning Portal
Modification Application1
Determination2
Consolidated Consent1
Ulan Coal Expansion MOD4 - Further Longwall Panel ChangesMP08_0184-Mod-4
/
Its 30 documents
30 documents in 5 folders, each on the NSW Planning Portal
Application1
Response to Submissions6
Recommendation10
Determination3
Ulan Coal Expansion MOD 3 - Longwall Panel ChangesMP08_0184-Mod-3
/
Its 20 documents
20 documents in 4 folders, each on the NSW Planning Portal
Application1
Response to Submissions2
Determination3
Mod 2 - Blasting & Mine PlanMP08_0184-Mod-2
Its 4 documents
4 documents in 2 folders, each on the NSW Planning Portal
Application1
Determination3
Mod 1 - Design ChangesMP08_0184-Mod-1
Its 11 documents
11 documents in 4 folders, each on the NSW Planning Portal
Application1
Submissions6
Response to Submissions1
Determination3
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
245 documents in 8 folders, each on the NSW Planning Portal
Application2
Request for DGRS1
Response to Submissions1
Determination5
Management Plans and Strategies99
Independent Reviews and Audits3
Other Documents27
What's near it
Its point is approximate (the register's own, to about a kilometre), and so are these.
Where it is
- Suburb
- Ulan
- Council area
- Mid-Western Regional
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.