Tweed Sand Plant Expansion
Expansion of the Tweed Sand Quarry at Cudgen
Where it is in the process
Approved on 24 Sep 2026
What it proposes
AI summary. Written from this project's page and its Tweed Sand Expansion Project Assessment Report and Tweed Sand Plant Expansion Notice of Decision on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Expansion of the Tweed Sand Quarry at Cudgen
The proposal would expand the Tweed Sand Quarry, a sand dredging operation off Crescent Street, Cudgen, in Tweed Shire. It seeks to extract 950,000 tonnes of sand a year, up from the 500,000 tonnes now allowed, across phases 5 to 11. Digging would form two artificial lakes within a 236 ha project area, and a new roundabout would give trucks direct access to the Pacific Motorway. It would provide 43 construction jobs and 18 operational jobs.
The environmental impact statement was exhibited from 22 Apr 2021 to 20 May 2021. It drew 16 submissions: 4 objecting and 12 comments. Tweed Shire Council objected over the final landform and long-term use of the site. The Executive Director of the department, acting for the Minister, approved it on 24 Sep 2026 with conditions, including a rehabilitation bond. Next, the proponent must meet those conditions.
- Proposed extraction rate
- 950,000 tonnes a yearTweed Sand Expansion Project Assessment Report
- Current approved extraction rate
- 500,000 tonnes a yearTweed Sand Expansion Project Assessment Report
- Total project area
- 236 haTweed Sand Expansion Project Assessment Report
- Construction jobs
- 43 jobsTweed Sand Plant Expansion Notice of Decision
- Operational jobs
- 18 jobsTweed Sand Plant Expansion Notice of Decision
- Virgin excavated material imported a year
- 60,000 tonnes a yearTweed Sand Expansion Project Assessment Report
The department's description
Expansion of the Tweed Sand Quarry extraction areas (Phases 5 to 11) and intensification of operations.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
16 submissions: 3 from the public, 1 from organisations and 12 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
184 documents in 8 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs17
- Att 01 - Concept Dev_Phasing Plan
- Att 02 - End Use Concept Plan
- Att 03 - Zoning & Prelim Analysis Plans
- Att 04 - Services Plans DBYD
- Att 05 - AHIMS Searches
- Att 06 - Lidar Contours
- Att 07 - Title Searches
- Att 08 - HTSP Phase 1-4 Approval
- Att 09 - DPIE Scoping Worksheet
- Att 10 - Scoping Consultation DPIE
- Att 11 - Scoping Consultation RMS
- Att 12 - Scoping Consultation TSC
- Att 13 - Community Consultation M&S Report
- Att 14 - VIA M&S
- Att 15 - TIA M&S Report
- Att 16 - KEI M&S Report
- Scoping Report
EIS42
- A10 Appendix - Tweed ACHMP
- A11 Appendix - Local Heritage Item Mapping
- A12 Appendix - Sensitive Receivers Dwellings
- A13 Appendix - Extraction Phasing Plan
- A15 Appendix - Conceptual Final Landform Plan
- A16 Appendix - Rehabilitation Phasing Plan
- A17 Appendix - Protected MST Results
- A18 Appendix - Bushfire Prone Land Mapping
- A19 Appendix - TSC Pre-Lodgement Meeting Minutes
- A8 Appendix - Sensitive Receivers Natural
- A9 Appendix - Agricultural Land Mapping
- Appendix - Existing & Proposed HTSP Footprint
- Appendix - PS & EW Lot & Plan Location
- Appendix - Services Diagrams
- Appendix - Site Layout Plans
- Appendix - Site Location (Local)
- Appendix - Site Location (Regional)
- Appendix - Unnamed RR Closure & Purchase
- Appendix - Zoning Plan
- Appendix B - Surface Water Assessment
- Appendix C - Ground Water Assessment
- Appendix D1 - Flood & Stormwater Assessment
- Appendix D2 - Flood Response Plan
- Appendix E - Soil & Water Management Plan
- Appendix F1 - Operational Noise Impact Assessment
- Appendix F2 - Construction Noise Assessment
- Appendix G - Air Quality Assessment
- Appendix H1 - BDAR
- Appendix H2 - Concept RLMP
- Appendix I - Aboriginal CHA
- Appendix J - Traffic Impact Assessment
- Appendix K - Acid Sulfate Soils Assessment
- Appendix L - Preliminary Site Investigation
- Appendix M - Agricultural Land Assessment
- Appendix N1 - Geotechnical Investigation
- Appendix N2 - Lake Bank Profiles
- Appendix O - Visual Impact Assessment
- Appendix P - Social Impact Assessment
- Appendix Q - Economic Impact Assessment
- Application_20210412225326
- CIV Doc - EIA
- EIS Main Report
Response to Submissions24
- Att 10 - Revised App A15 - Concept Final LP
- Att 11 - Revised App A16 - Rehab Phasing Plan
- Att 12 - Supplementary Water Quality Report - MIC
- Att 13 - Supplementary Groundwater Model Report
- Att 14 - Supplementary WBM Report
- Att 15 - Revised App F1 - ONIA
- Att 16 - Revised App F2 - CNA
- Att 17 - Revised App O - VIA
- Att 18 - Revised App Q - EIA
- Att 19 - Revised App I - ACH Assessment
- Att 1A - Submission Response Table
- Att 1B - G&S Response Comments
- Att 1C - TBLALC Correspondence
- Att 1D - JWA Bio & Rehab Response Comments
- Att 2 - Revised Appendix D1 - Flood & SA
- Att 3 - Revised Appendix G - AQA
- Att 4 - Revised Appendix H1 - BDAR
- Att 5 - Revised Appendx H2 - CRLMP
- Att 6 - Revised Appendix J - TIA
- Att 7 - Revised App A3 - Ext & Prop HTSP Footprint
- Att 8 - Revised App A13 - Extraction PP
- Att 9 - Revised App A14 - Site Layout Plan
- Request RTS_23052021_101305
- Submission Report
Agency Advice26
- BCD - RTS
- BCD Advice - EIS
- BCD Response Request for SEARS Tweed Sand
- DPI Agriculture - EIS
- DPI Agriculture - RTS
- DPI advice - Hanson Tweed Sand Plant Expansion
- DPIE Water - EIS
- DPIE Water - RTS
- EPA - EIS
- EPA - RTS
- EPA SEARs Hanson Tweed Sand SSD10398
- Hanson letter Sept
- Hanson prelodg attachment
- HansonTweedSandPlantExp(SSD-10398)-SEARs-DRG
- Heritage Council of NSW - EIS
- Heritage NSW - EIS
- Mining, Exploration and Geoscience - EIS
- SSD 10398 - Hanson Tweed Sand Plant Expansion
- SSD10398 TfNSW Response
- TfNSW - EIS
- TfNSW - RTS
- TfNSW Advice Response
- Tweed Council
- Tweed Shire Council - EIS
- Tweed Shire Council - RTS
- Water response - (SSD 10398)
Additional Information68
- Additional Information Transport 19 June 2025
- April 2022 RFI Cover Letter
- Att 14 - Revised App N2 - Lake Bank Profiles
- Att 3 - Revised App D1 - F & S Assessment - Part 2
- Att 3 - Revised App D1 - F & S Assessment - Part 3
- Att 4 - Revised Appendix H1 - BDAR
- Att 5 - Revised App H2 - Concept RLMP
- Att 6 - Revised App J - TIA
- Att 7 - Revised Supplementary WB Modelling Report
- Att 8 - Revised Supplementary Haulage Route Econ Eval
- Att 9 - Revised Supplementary Concept Mine Closure Plan
- BCD Advice 3 Dec 2021
- BCD Comments 6 July 2022
- BCD Comments on spatial data July 2021
- BCS Comments 12 July 2024
- Concept Mine Closure Plan April 2022
- DPE Water 24 July 2023
- DPE Water Response 20 July 2022
- DPIE Water Response 10 Dec 2021
- EPBC Act 1999 Referral Response
- EPBC Act 1999 Referral Response
- FINAL TSC Comments July 2025
- Flood & Stormwater Assessment April 2024
- G&S Response to BCD Comments 28 May 2025
- G&S Response to BCD Comments 28 May 2025
- Hanson Response to Water Issues 9 May 2023
- Hanson TSP to DPE Response to RFI 29 June 2022
- Human Health & Environmental Risk Assessment May 2023
- Independent Review Final Landform
- JWA Response Letter April 2022
- Martens Flooding Response TSC 18 Dec 2024
- Martens Response Letter 181224
- Martens Response Letter 181224
- RFI Addendum 15 Dec 2021
- RFI Request 13 Dec 2022
- RFI Request 17 Feb 2022
- RFI Request 23 Nov 2021
- RFI Request August 2022
- RFI Request for Additional Information 2 Nov 2021
- RFI Request on BCD Advice
- RFI Response Report
- Request for Additional Information_15042025_110018
- Request for Additional Information_18082025_032622
- Request for Additional Information_22122025_031534
- Request for Information 19 June 2025
- Response to ABLP Letter June 2024
- Response to BCD Comments 3 Sept 2024
- Response to BCD Letter - BCD RFI June 2024
- Response to BCD RFI 29 May 2025
- Response to BCD RFI Table 29 May 2025
- Response to DPE RFI - June 2024
- Response to DPE Water RFI 20 July 2022
- Response to DPE Water RFI 24 July 2023
- Response to DPIE RFI 19 Nov 2021
- Revised BDAR April 2022
- Revised BDAR May 2025
- Revised Concept Mine Closure Plan May 2025
- Revised Concept RLMP April 2022
- Revised Concept RLMP May 2025
- Revised EIS Figures May 2025
- Revised Flood & Stormwater Assessment April 2024
- Revised Soil & Water MP May 2023
- Revised Soil Water MP April 2022
- Revised VIA May 2025
- Supplementary Flood Model Peer Review 17 May 2024
- Supplementary Flood Modelling
- TSC RFI Response Summary Table_B May 2025
- Tweed Shire Council - Flooding Comments 29 November 2024
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.