On the map
State significant development

Tweed Sand Plant Expansion

Expansion of the Tweed Sand Quarry at Cudgen

Decided: approved on 24 Sep 2026QuarriesDistrict scale

Where it is in the process

Approved on 24 Sep 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination24 Sep 2026 (done)
  9. Approved24 Sep 2026

What it proposes

AI summary. Written from this project's page and its Tweed Sand Expansion Project Assessment Report and Tweed Sand Plant Expansion Notice of Decision on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Expansion of the Tweed Sand Quarry at Cudgen

The proposal would expand the Tweed Sand Quarry, a sand dredging operation off Crescent Street, Cudgen, in Tweed Shire. It seeks to extract 950,000 tonnes of sand a year, up from the 500,000 tonnes now allowed, across phases 5 to 11. Digging would form two artificial lakes within a 236 ha project area, and a new roundabout would give trucks direct access to the Pacific Motorway. It would provide 43 construction jobs and 18 operational jobs.

The environmental impact statement was exhibited from 22 Apr 2021 to 20 May 2021. It drew 16 submissions: 4 objecting and 12 comments. Tweed Shire Council objected over the final landform and long-term use of the site. The Executive Director of the department, acting for the Minister, approved it on 24 Sep 2026 with conditions, including a rehabilitation bond. Next, the proponent must meet those conditions.

Proposed extraction rate
950,000 tonnes a yearTweed Sand Expansion Project Assessment Report
Current approved extraction rate
500,000 tonnes a yearTweed Sand Expansion Project Assessment Report
Total project area
236 haTweed Sand Expansion Project Assessment Report
Construction jobs
43 jobsTweed Sand Plant Expansion Notice of Decision
Operational jobs
18 jobsTweed Sand Plant Expansion Notice of Decision
Virgin excavated material imported a year
60,000 tonnes a yearTweed Sand Expansion Project Assessment Report

The department's description

Expansion of the Tweed Sand Quarry extraction areas (Phases 5 to 11) and intensification of operations.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

16 submissions: 3 from the public, 1 from organisations and 12 from public authorities

Object4
Support0
Comment12

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

184 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs17
SEARs3
EIS42
Response to Submissions24
Agency Advice26
Additional Information68
Determination3

What's near it