On the map
State significant development

Tocumwal Magazine Storage Upgrade

Four new explosives magazines at Tocumwal, Newell Highway

Under way: at assessmentIndustry and warehousesLocal scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its 12597123-REP-0_Orica Tocumwal Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Four new explosives magazines at Tocumwal, Newell Highway

Orica proposes to build four new 250 t high explosive magazines and a new detonator magazine at the Tocumwal Explosives Reserve, 431 Newell Highway, about four kilometres north of Tocumwal in the Berrigan Shire. The site is about 750 ha. The existing ten magazines do not meet the Australian Standard for explosives storage and operate under an exemption. The same quantity of explosives would be stored and operations would stay unchanged. Most old magazines would be demolished and two reused for other storage. No capital investment is stated.

The case is at the stage where the department has requested more information. The environmental impact statement (EIS) has been exhibited and the proponent has responded and amended the project, but the exhibition dates are not stated. One submission was made, a comment from an organisation. Next, the department assesses the project once it has the information it needs, then prepares an assessment report and the project is determined.

New high explosive magazines
4 magazines12597123-REP-0_Orica Tocumwal Scoping Report
Capacity of each new magazine
250 tonnes12597123-REP-0_Orica Tocumwal Scoping Report
Existing magazines
10 magazines12597123-REP-0_Orica Tocumwal Scoping Report
Site area
750 ha12597123-REP-0_Orica Tocumwal Scoping Report

The department's description

Construction and operation of four new 250t high explosive magazines and a new detonator magazine storage buildings

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

1 submission: 1 from organisations

Object0
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

51 documents in 9 folders, each on the NSW Planning Portal

Early Consultation2
Notice of Exhibition1
Request for SEARs2
SEARs3
EIS11
Response to Submissions4
Agency Advice14
Amendments2
Additional Information12

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.