On the map
State significant development

South Coree Battery Energy Storage System

An 80 MW battery on Broockmanns Road, Finley

Under way: at assessmentEnergy: batteriesNeighbourhood scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its South Coree Battery Energy Storage System EIS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

An 80 MW battery on Broockmanns Road, Finley

The proponent proposes to build, operate and later decommission a battery energy storage system with a capacity of 80 MW and 320 MWh, with associated infrastructure, at 384 Broockmanns Road, Finley, in the Berrigan Shire Council area. The environmental impact statement (EIS) is dated October 2025. No capital investment or job numbers are stated.

The EIS was exhibited and drew 63 submissions: 62 objecting and 1 commenting. The proponent responded to submissions and amended the project; an amendment was accepted in June 2026. The department asked for more information on 12 Aug 2026 and again, in amended form, on 28 Aug 2026. The proponent replied on 15 Sep 2026 and 17 Sep 2026. Next, the department continues its assessment with advice from other agencies and then prepares its assessment report. A decision follows.

Battery power capacity
80 MWPortal page
Battery storage capacity
320 MWhPortal page
Submissions
63 submissionsPortal page
Submissions objecting
62 submissionsPortal page

The department's description

The construction, operation and decommissioning of a battery energy storage system with a capacity of 80 MW / 320 MWh, and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

63 submissions: 51 from the public and 12 from organisations

Object62
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

76 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs1
EIS15
Response to Submissions7
Agency Advice40
Amendments5
Additional Information6

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.