On the map
State significant development

Tinda Creek Quarry

Decided: approved on 10 Apr 2015Quarries

Where it is in the process

Approved on 10 Apr 2015

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination10 Apr 2015 (done)
  9. Approved10 Apr 2015

What it proposes

The department's description

Tinda Creek Quarry

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

2 submissions: 1 from the public and 1 from organisations

Object2
Support0
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Tinda Creek Quarry - Tinda Creek Quarry - Modification 1 - Water ManagementSSD-4978-Mod-1

Under way: at assessment

To undertake controlled discharge from site.

Its 24 documents

24 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Early Consultation1

See the document on the Planning Portal

SEARs3

See the 3 documents on the Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice12

See the 12 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.