On the map
State significant development

Tilbuster Solar Farm

Decided: approved on 3 Mar 2022Energy: solarDistrict scale

Where it is in the process

Approved on 3 Mar 2022

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination3 Mar 2022 (done)
  9. Approved3 Mar 2022

What it proposes

The department's description

The development of a 150 MW solar farm, energy storage facility and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

28 submissions: 9 from the public and 19 from public authorities

Object6
Support4
Comment18

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Tilbuster Solar Farm - Modification 1SSD-9619-Mod-1

Decided: approved on 4 Sep 2026 by the department (director)

Seeks to modify the development consent to alter: - the development footprint - weekend work hours - port options - OSOM definition

Its 32 documents

32 documents in 5 folders, each on the NSW Planning Portal

Modification Application10

See the 10 documents on the Planning Portal

Agency Advice12

See the 12 documents on the Planning Portal

Additional Information7

See the 7 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.