On the map
Part 4 development

Teys (formerly Cargill) Beef Abattoir

Decided: decidedIndustry and warehouses

Where it is in the process

At determination

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (current stage)

What it proposes

The department's description

The Minister for Planning has given approval to Cargill Foods Australia Pty Ltd to upgrade and expand its existing abattoir at Bomen Road, Wagga Wagga.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

10 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 4 - Wastewater System UpgradeDA220-07-2002-i-Mod-4

Decided: approved by the department (director)

Its 10 documents

10 documents in 3 folders, each on the NSW Planning Portal

Application7

See the 7 documents on the Planning Portal

Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 3DA220-07-2002-i-Mod-3

Decided: approved by the department (director)

Its 6 documents

6 documents in 2 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

Assessment3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 2DA220-07-2002-i-Mod-2

Decided: approved by the department (director)

Its 2 documents

2 documents in 2 folders, each on the NSW Planning Portal

SEE1

See the document on the Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 1 - Layout AmendmentsDA220-07-2002-i-Mod-1

Decided: approved by the Independent Planning Commission

The proposed modification involves modifying the layout of the abattoir, carparking area and cattle yards to improve the operational performance of the abattoir.

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

SEE1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Teys Abattoir MOD 10 - Alterations to ASRS BuildingDA220-07-2002-i-Mod-10

Decided: approved on 23 Oct 2018 by the department (director) · 1 submission

The proposed modification would involve alterations and additions to the previously approved Auto Sortation and Retrieval System (ASRS) Building, and retention of the existing battery recharge building.

Its 17 documents

17 documents in 3 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

EIS12

See the 12 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Teys Abbatoir MOD 9 - Chiller Facility AwningDA220-07-2002-i-Mod-9

Decided: approved on 12 Jan 2017 by the department (director)

The proposed modification seeks to construct a 233 square metre awning over an annex of the existing chiller building.

Its 7 documents

Its page on the Planning Portal

Teys Abbatoir MOD 8 - Cattle Yard ExpansionDA220-07-2002-i-Mod-8

Decided: approved on 11 Oct 2016 by the department (director) · 2 submissions

The modification request seeks to: - increase the existing cattle stockyards by approximately 500 sqm with an additional shade structure; - install a skillion awning approximately 120 sqm on an existing box room; and - demolish a portable office.

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

EA3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Teys Abattoir MOD 7 - Biofilter ReplacementDA220-07-2002-i-Mod-7

Decided: approved on 13 Jan 2016 by the department (director) · 1 submission

Teys Australia Wagga Wagga are seeking to modify DA220-07-2002-i for the Beef Abattoir at Bomen to construct a replacement bio-filter and demolition of the existing bio-filter to manage air quality and odour from the operation.

Its 7 documents

Its page on the Planning Portal

Teys Abattoir MOD 6 - Processing facility upgradesDA220-07-2002-i-Mod-6

Decided: approved on 7 Jul 2015 by the department (director)

Modifications to the existing beef processing facility at Bomen involving: -reinstatement of a former heavy vehicle access point off Dampier Street; -construction of additional cold storage and palletising space; -construction of a new loading dock;

Its 15 documents

Its page on the Planning Portal

Mod 5 - Additional Irrigation AreaDA220-07-2002-i-Mod-5

Decided: approved on 28 Sep 2011 by the department (executive director)

The proposed modification involves irrigation of treated wastewater produced on-site onto a parcel of land to the south of the existing irrigation area.

Its 14 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

15 documents in 5 folders, each on the NSW Planning Portal

EIS5

See the 5 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Management Plans and Strategies2

See the 2 documents on the Planning Portal

Reports1

See the document on the Planning Portal

Independent Reviews and Audits3

See the 3 documents on the Planning Portal

What's near it