State significant development

Talbingo Battery Energy Storage System

A 450 MW battery on Miles Franklin Drive, Talbingo

Under way: at prepare eisEnergy: batteriesDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 450 MW battery on Miles Franklin Drive, Talbingo

The proponent proposes to build, operate and later decommission a battery energy storage system of up to 450 MW and 1,800 MWh (four hours of storage) at 563-571 Miles Franklin Drive, Talbingo, in the Snowy Valleys Council area. The site is about 2.8 km south-west of Talbingo, next to the Lower Tumut 330 kV Switching Station, which it would connect to by overhead transmission lines. The project site is about 31 ha, with about 8 ha for the batteries. No capital investment is stated.

The case is at the stage where the proponent prepares an environmental impact statement (EIS). The scoping report's final version is dated 29 Nov 2024. The Secretary's environmental assessment requirements (SEARs) have been issued, and a later amendment changes the battery capacity. No submissions have been made yet. Next, the proponent lodges the EIS, which is exhibited for public submissions before the department assesses it.

Battery power capacity
450 MWScoping Report
Battery storage capacity
1,800 MWhScoping Report
Project site area
31 haScoping Report
Battery siting area
8 haScoping Report

The department's description

Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 450MW/1800MWh and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.