Snowy 2.0 - Main Works

Decided: approved on 20 May 2020Other

Where it is in the process

Approved on 20 May 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination20 May 2020 (done)
  9. Approved20 May 2020

What it proposes

The department's description

The development of an underground pumped hydro power station and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

201 submissions: 160 from the public, 31 from organisations and 10 from public authorities

Object147
Support11
Comment43

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 4 - Southern Communication LineSSI-9687-Mod-4

Under way: at exhibition

Installation and operation of a 16 km communication line (fibre optic cables) from Marica to the Selwyn Ski Field carpark, replacing a 35 km section of the approved communication line.

Its 14 documents

14 documents in 3 folders, each on the NSW Planning Portal

SEARs1

See the document on the Planning Portal

Modification Application12

See the 12 documents on the Planning Portal

Exhibition1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 3 - Additional AditSSI-9687-Mod-3

Decided: approved on 17 Dec 2024 by the department (executive director) · 24 submissions

Modification includes excavating an additional adit at Marica West to facilitate progression through the Long Plain Fault Zone.

Its 33 documents

33 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information13

See the 13 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 2 - Remediation and Ground ConsolidationSSI-9687-Mod-2

Decided: approved on 30 Nov 2023 by the department (director) · 5 submissions

Remediation of sinkhole and ground consolidation works to facilitate the progression of TBM Florence at Tantangara

Its 19 documents

19 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice7

See the 7 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 1 - Main Access Tunnel to Marica Services ConnectionSSI-9687-Mod-1

Decided: approved on 28 Jan 2022 by the department (director) · 5 submissions

Modification to permit horizontal directional drilling for utilities/services between the Lobs Hole and Marica areas of the project

Its 17 documents

17 documents in 5 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice9

See the 9 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.